Cryonics Institute Sprinkler System
by Ben Best
For many years we at CI have felt that the expense of a sprinkler
system was not justified for the CI Facility. There is very little
that is flammable, drywall is protective and the cryostats are coated
with or imbedded with fire retardant. The older (rectangular) cryostats
were constructed with 10% antimony trioxide fire retardant incorporated into
the fiberglass-resin composite. The HSSV-6 cylindrical cryostats are coated
with a fire retardant known as
Fire-Free 88,
which we selected after exhaustive research into the market for retardants.
Facilities Manager Andy Zawacki demonstrated that three coats
of FF88 could withstand a full minute of the hottest portion of a
blowtorch without penetration.
However, the American Cryonics Society has 18 patients stored at
CI and they offered to pay half the cost of putting a sprinkler system
in the building. Bids were taken from three contractors, and after
checking references and prices a contract was accepted by Interstate
Fire Protection, Inc. First the building was filled with pipes and
sprinkler heads by a pipefitter and his assistant, then subcontractors
(a husband and wife team) connected the pipes in the CI Facility to
the water main running on the other side of the street by digging
up the road and making a trench along the side of the CI Facility.
Below is a photo essay of the project.
Pipes ready for mounting
|
Mounting a pipe
|
Sprinkler goes into office
|
Sprinkler goes into boardroom
|
Black pipes for sprinkler, silver pipes for liquid nitrogen
|
Husband with jackhammer
|
Wife with shovel
|
Unfortunately, the water main for Sorrentino Court lies on the opposite side of
the street from the CI building. This meant that to tap the water main for the
additional water that the sprinkler system would require meant digging up the
street -- adding substantially to the cost of the system. Also unfortunately,
when digging across the street to reach the water main, the pipe running
into our neighbor's building was struck and water gushed-out, filling
the hole that was being dug. As a neighborly gesture, we invited the neighbor's
to use the toilet in our building, if needed.
Big shovel breaks a water pipe
|
Big shovel bailing water
|
Neighbors get new water pipe
|
Water main is exposed
|
Hole drilled into water main
|
Enough work for one day
|
CI Building across the street from the water main
|
Not only men were working
|
Husband with big shovel
|
Wife with little shovel
|
Digging across the whole street
|
Continue digging between buildings
|
Digging to reach the perfusion room
|
Bailing wet mud from hole by perfusion room
|
Inlet for water from fire truck
|
Tapping water from the main
|
Chlorine flushed from pipe in perfusion room
|
Water runs through the building and down the drain
|
Concrete poured into street
|
Concrete spread on north half of street
|
South half of street ready for concrete
|
Concrete spread on south side of street
|
Concrete spread on perfusion room
|
Installation of control valves in perfusion room
|
Fully installed control valves in perfusion room
| Front View | Side View |
|
|
Alarm and water inlet on the outside of the building
|